Hello everyone! I have been working on updating and make RCTP 3D! This airport is the largest in Taiwan, and serves as a hub for Eva Air and China Airlines. The 2D for this airport is also heavily outdated, so I have been working on a complete overhaul from scratch (don’t be surprised if you see me taxiing around RCTP on non-existent taxiways).

Construction Roadmap
Stage Details Completed
2D:
1 Pavements 28th November 2022
2 Main Taxiway Lines 3rd December
3 Hold and Misc Taxiway Lines 9th December
4 Road Lines 9th December
5 Start Locations 11th December
3D:
6 North Cargo Apron 12th December
7 South Cargo Apron 13th December
8 CAL Maintenance Apron 14th December
9 EVA Maintenance Aprons 15th December
10 Remote Parking Aprons 16th December
11 Main Remote Apron 17th December
12 Misc Buildings 21st December
13 Terminal 1 Main Building 31st December
14 Concourse A Building 1st January 2023
15 Concourse A Jetbridges/Objects 3rd January 2023
16 Concourse B Building 3rd January
17 Concourse B Jetbridges/Objects 3rd January
18 Terminal 2 Main Building 5th January
19 Concourse C Building 10th January
20 Concourse C Jetbridges/Objects 12th January
21 Concourse D Building 14th January
22 Concourse D Jetbridges/Objects 15th January
23 Connector rails 15th January
Misc:
24 Misc Objects + Settings 15th January
25 Peer Review 18th January (by @med_hadi.a)
26 Official Review 6th February (by @Fergus)


Photo credit: RCTP | Airport | Airport Overview | nguyenphuong | JetPhotos
Credit to @Tobias_HSU and @TaipeiGuru for helping me with all the charts and reference images to make RCTP as realistic as possible!

23 Likes

Hello! I’m Taiwanese aviation lover~ First of all, thanks for making RCTP in 3D. 🥹
If you need any help of the airport detail, feel free to contact me!

4 Likes

UPDATE

  • 2D work is complete
  • The construction roadmap is updated with the 3D plan
  • I aim to have this airport done by 30th December

Here is a WiP of the Southern cargo apron (Stands 501-515):
image
The Northern cargo stands are also complete, and will move onto the maintenance aprons now

18 Likes

OMG thank you so much!!!

1 Like

Good job man, I got a question, so, this is going to be finished by the end of the year?

I think Ill be finished in the first week of January, as im currently on holiday abroad

2 Likes

UPDATE #2

  • More 3D work is done, including: Tower area, maintenance aprons and remote aprons
  • Work on the main terminal buildings will begin now
  • Due to the holiday season, I am on holiday abroad (as well as revising for national level exams) and the expect time of completion is around the start of January
  • However, enjoy this WiP in the meantime of the CAL apron and the towers in the background!

    Note: I have been notified the old tower has been torn down. I will make the change and remove it

CAN YOU BE THE FIRST TO FIND MORITZ?

(Its not very hard)

Happy holidays to all! Stay safe!

15 Likes

I’ll be so excited to fly Into Taipei once it’s 3D (hoping for a 23.1 release), keep the good work!

4 Likes

https://www.instagram.com/p/CpvknbfuC_i/?igshid=YmMyMTA2M2Y=
👀 Sorry I havent posted updates recently here, but if you havent seen already and you’ve been waiting…

5 Likes

I saw that yesterday! Well done guys!

4 Likes